Note: This is not a PennEast post. This is about the South Hunterdon School District referendum being voted on in November on whether or not to finance $26 million on school facilities. Jim Galla...
As many of you know, yesterday PennEast cried uncle and threw in the towel. Here full statement they emailed to various media outlets: Against all odds, in a fight everyone said we could never wi...
https://thecostofthepipeline.com/2021/09/28/na-na-na-na-na-na-na-na-hey-hey-goodbye/
On June 29th, 2021, the Supreme Court finally ruled on the case PENNEAST PIPELINE CO., LLC v. NEW JERSEY ET AL. This was the case centering around eminent domain authority, and the State of New...
https://thecostofthepipeline.com/2021/07/02/supreme-court-loss-isnt-what-some-people-think-it-is/
“No reliance on PennEast” Yesterday, New Jersey Resources held its 2020 “Analyst’s Day”, when it woos financial analysts to pitch their financial story for growth. In a surprise twist, ...
https://thecostofthepipeline.com/2020/12/01/new-jersey-resources-loses-confidence-in-penneast/
Today 13 grassroots organizations, environmental groups, and individuals came together and submitted an extensive set of comments to the Delaware River Basin Commission on the PennEast Pipeline a...
Yesterday, PennEast’s lawyers submitted a brief to the Supreme Court attempting to rebut the State of NJ’s brief in opposition of the Court taking up PennEast’s case. The brief was astonish...
https://thecostofthepipeline.com/2020/06/10/penneasts-lawyers-have-run-out-of-arguments/
See this mailchimp campaign… https://mailchi.mp/a473a705f720/action-alert-please-submit-this-comment-to-ferc
https://thecostofthepipeline.com/2020/05/05/action-alert-send-a-comment-to-ferc-today/
Last Friday, May 1, 2020, PennEast filed a response to FERC’s April 1, 2020 Data Request on docket CP20-47-000. As you might expect, while reading the response the image of the Keystone Kops tr...
https://thecostofthepipeline.com/2020/05/05/penneast-cant-help-but-trip-over-itself/
Today, 13 groups and individuals filed a Motion with FERC demanding that PennEast reveal the true nature of the precedent agreements attached to Phase 1 and Phase 2 of the project. The need for...
Today I filed a Motion for Leave to Answer and Answer with FERC to PennEast’s response this week to FERC’s April Data Request. The full filing is available here: https://elibrary.ferc.gov/idm...